AB 2109 (Carrillo), the CLECA-sponsored law that exempts industrial process heat recovery from nonbypassable and departing load charges, was signed in September 2024. It left two things for the Commission to decide: which charges the exemption covers, and a cap on how much load can use it. That work is now under way in the Advanced Electric Rate Design rulemaking (R.26-04-009).
The schedule
- September 22, 2026. The Assigned Commissioner's scoping memo placed AB 2109 in Track 3 of the rulemaking, found no evidentiary hearings are needed, and targeted a proposed decision for the first quarter of 2027.
- October 30, 2026. PG&E, Southern California Edison, and SDG&E filed their joint implementation proposal.
- December 7, 2026. Opening comments on the proposal are due.
- December 22, 2026. Reply comments are due.
What the utilities proposed
The cap. Each utility would have its own cap, set in megawatts at 50 percent of the load the utility estimates could install qualifying equipment. For PG&E that is 12 MW, half of an estimated 24 MW. SDG&E's cap would be zero. Edison did not publish its figure, citing customer confidentiality rules. The utilities also ask the Commission to rule out future increases.
The sunset. The exemption would end after ten years.
Reserving capacity. Capacity under the cap would be reserved first come, first served. Once a utility accepts a project, the customer would have 24 months to reach permission to operate or forfeit the reservation, with extensions only in "very limited extenuating circumstances." Participating customers would recertify every three years.
What it would cost other customers
The statute tells the Commission to minimize cost impacts on customers who do not participate. By the utilities' own estimate, at the proposed caps the exemption shifts about $7.6 million a year in PG&E's territory and $6.5 million in Edison's. That is a system average rate impact of roughly 0.04 percent, or about four to five cents a month on a typical residential bill.
What to watch
CLECA will respond in comments on December 7. The question running through all of it is whether the proposal is workable for a manufacturer deciding whether to build.
- The cap. AB 2109 already limits each project to 25 percent of a customer's peak load. A cap at half the eligible market, with no path to raise it, leaves room for only some of the facilities the Legislature had in mind.
- The sunset. Heat recovery systems are long-lived capital projects. A benefit that expires in ten years is worth much less to a facility weighing the investment.
- The 24-month window. Engineering, permitting, procurement, and construction for an industrial heat recovery project commonly take longer than two years. A reservation that lapses at 24 months does not match realistic development timelines, and a project that loses its place under a small cap may not get it back.
Both houses passed AB 2109 without a no vote. The remaining job is to implement it in a form manufacturers can use. Background: the case for AB 2109 and CLECA's comments in the rate design rulemaking.